Project Timeline Example

Below is an example timeline for constructing a two-storey home extension that includes a new kitchen on the ground floor and a bedroom (or additional living space) on the upper floor. Note that actual timelines can vary based on location, project size, and local regulatory requirements…

1
Initial Consultation & Feasibility Study

Meet with an architect and contractor to discuss your vision and assess feasibility.

2
Budgeting & Financing

Establish a preliminary budget and secure financing if needed.

3
Conceptual Design

Develop initial sketches and layouts for the kitchen and bedroom extension.

4
Detailed Design & Planning

Finalise architectural drawings and layout details, including room sizes, staircase placement, and integration with the existing structure.

5
Planning Permission

Submit designs to the local authority and obtain necessary planning permissions.

5
Planning Permission

Submit designs to the local authority and obtain necessary planning permissions.

6
Structural & Engineering Consultations

Engage structural engineers to assess the load-bearing requirements and ensure the extension’s design is safe and compliant.

7
Contractor Selection & Tender Process

Solicit bids from contractors and select the one that best meets your project needs.

8
Final Budget Approval & Contract Signing

Confirm detailed costings with your contractor and sign contracts outlining project milestones and deliverables.

9
Site Preparation

Prepare the construction site, including setting up temporary fencing, signage, and any required utility diversions.

10
Demolition/Clearing

Remove any existing structures or obstacles in the extension area.

11
Foundation Excavation & Laying Footings

Excavate the site and construct foundations and footings for the extension.

12
Ground Floor Construction

Build the ground floor framework, including walls and the base for the new kitchen area.

13
First Storey Construction

Construct the upper floor framework that will house the bedroom or additional living space, including stairs and supporting structures.

14
Roof Construction & Installation

Install the roof framework and complete roofing works, ensuring proper insulation and weatherproofing.

15
Installation of Windows, Doors & External Cladding

Fit external windows and doors and install cladding or other exterior finishes.

16
Electrical and Plumbing

Install preliminary electrical wiring, plumbing, systems throughout the new extension.

17
Internal Walls & Insulation

Construct internal partition walls, install insulation, and complete any necessary soundproofing between levels.

18
Flooring, Tiling & Basic Interior Finishes

Lay down flooring, install tiling in wet areas, and complete base interior finishes.

19
Kitchen & Bathroom Fixtures Installation

Install cabinetry, countertops, appliances in the kitchen, and fixtures in the bathroom (if included in the extension).

20
Final Touches, Inspection & Handover

Complete painting, decoration, and finishing touches; conduct final inspections and secure approval before officially handing over the completed extension.

This timeline serves as a general guide.

Coordination among architects, engineers, contractors, and local authorities is crucial to ensure the project runs smoothly and meets all regulatory requirements.