Below is an example timeline for constructing a two-storey home extension that includes a new kitchen on the ground floor and a bedroom (or additional living space) on the upper floor. Note that actual timelines can vary based on location, project size, and local regulatory requirements…
Meet with an architect and contractor to discuss your vision and assess feasibility.
Establish a preliminary budget and secure financing if needed.
Develop initial sketches and layouts for the kitchen and bedroom extension.
Finalise architectural drawings and layout details, including room sizes, staircase placement, and integration with the existing structure.
Submit designs to the local authority and obtain necessary planning permissions.
Submit designs to the local authority and obtain necessary planning permissions.
Engage structural engineers to assess the load-bearing requirements and ensure the extension’s design is safe and compliant.
Solicit bids from contractors and select the one that best meets your project needs.
Confirm detailed costings with your contractor and sign contracts outlining project milestones and deliverables.
Prepare the construction site, including setting up temporary fencing, signage, and any required utility diversions.
Remove any existing structures or obstacles in the extension area.
Excavate the site and construct foundations and footings for the extension.
Build the ground floor framework, including walls and the base for the new kitchen area.
Construct the upper floor framework that will house the bedroom or additional living space, including stairs and supporting structures.
Install the roof framework and complete roofing works, ensuring proper insulation and weatherproofing.
Fit external windows and doors and install cladding or other exterior finishes.
Install preliminary electrical wiring, plumbing, systems throughout the new extension.
Construct internal partition walls, install insulation, and complete any necessary soundproofing between levels.
Lay down flooring, install tiling in wet areas, and complete base interior finishes.
Install cabinetry, countertops, appliances in the kitchen, and fixtures in the bathroom (if included in the extension).
Complete painting, decoration, and finishing touches; conduct final inspections and secure approval before officially handing over the completed extension.
Coordination among architects, engineers, contractors, and local authorities is crucial to ensure the project runs smoothly and meets all regulatory requirements.
Cookie | Duration | Description |
---|---|---|
cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |